Implementation
Cyclists
The map on the right shows the construction status as of April
2006.
The city released an implementation plan in early June 2003. The plan
establishes priorities for the bike routes:
Relative Greenway and Pedestrian Priorities. Greenway projects were
ranked from highest to lowest as follows: Granville Street, Carrall Street,
Helmcken Street, Comox Street, Lagoon Drive and Port Road corridor. Other
pedestrian route priorities will be based on considerations of pedestrian
volumes, connectivity to major downtown nodes, safety and security
concerns, adjacent development potential, existing street conditions and
community support.
Relative Bike Route Priorities. Based on the need to develop a basic
bike route network that provides key access into and across the downtown in
the short term, the bike routes shown in Figure 2 are recommended for
earlier implementation. They include bike lanes along Burrard, Hornby,
Georgia, Pender, Dunsmuir, Pacific and Expo Boulevard. Any bike lanes on
Pender Street must first be preceded by a study with TransLink to determine
the feasibility of converting a portion of Pender Street from a two-way to
a one-way street.
[City administrative report, Transportation and Traffic Committee, June 10, 2003]
Based on this plan, the following should be implemented by early
2006:
- Design and implement Pender-Adanac Bike Connection
- Design and implement bike lanes on Burrard
- Detailed design of Pacific Boulevard/Street (Burrard to Nelson)
- Reconstruction of Pacific Boulevard/Street (Burrard to Nelson)
- Design and implement bike lanes on Pacific and Expo Boulevard
- Design and implement bike lanes on Hornby
- Design and implement bike lanes on Pender/Dunsmuir
- Further evaluate Pender Street conversion to 1-way
- Implement Pender Street recommendation
- Construct bike lanes on Georgia Street west of Pender
- Design bike lanes on Carrall Street
- Report back on ongoing study of ped/bike upgrades on Granville Bridge
- Prepare detailed design for upgrading pedestrian/bike facilities on
Burrard Bridge
- Implement Street Furniture Program - pedestrian/bike facilities
- Make existing West End local traffic barriers bike friendly
- Improve cyclists' connection(s) through Science World area
- Design Carrall Street Greenway
- Convert Carrall Street (Hastings-Pender) to 2-way
- Convert Beatty Street to 2-way
- Implement 40 km/h traffic signal progression on selected streets
City council approved $992 000 to hire more staff to complete the following
additional items by early 2006:
- Design and implement bike lanes on Beatty
- Design bike lanes on Richards
- Design the Chilco Street Bikeway
- Design the Cardero Street Bikeway
- Design bike lanes on Alberni/Jervis/Haro
- Review bike lanes on Georgia leading to the viaduct
- Review bike lanes on Robson east of Richards
- Review bike lanes on Homer south of Dunsmuir
- Design Helmcken/Comox Street Greenway
- Design Lagoon Drive Greenway with Park Board
- Redesign Intersection of Carrall/Powell/Water/Alexander
The only implementation date the city has firmly committed to is 2006.
However, based on discussions with city staff, approximate dates for the
completion of many routes are known:
- Georgia: fall 2003.
- Pacific/Expo Blvd.: fall 2003 for Homer to Quebec
section; summer 2006 for Seymour to Richards section; no date yet for
Burrard to Seymour or Richards to Homer. The Homer to Nelson section may be
replaced by a redesigned configuration eventually.
- Pacific St.: 2006 is possible for one section; the section west of
Burrard St. remains unknown.
- Hornby: June 2005.
- Richards: April 2006.
- Homer: May 2005.
- Beatty: May 2005.
- Burrard: August 2005.
- Chilco: June 2006.
- Cardero: June 2006.
- Pender: 2008? Further delays, allegedly due to Canada Line
construction.
- Dunsmuir: June 2006.
- Carrall: 2007. Approved by council in June 2006. Two-way
conversion of northern sections of Carrall was completed in April 2004.
- Haro/Nicola: 2006-2007? Approved by council in July 2005. City construction
appears to be backlogged and may push this to 2007.
- Comox/Helmcken: 2008? Design will begin once the team working on
Carrall is done.
- Beach: unknown.
- Port Road: unknown.
- Viaducts: the Dunsmuir viaduct (and possibly also the Georgia viaduct)
will be done when the Costco development completes, likely in early 2007.